Bellpower
Power:
9.2 MW
Location:
Italy - Monteruga (Puglia)
Status:
Completed
Scope:
Turn Key Project
Technology:
Fixed
This project consists of a photovoltaic plant of 9 MW built in only one phase with a fixed structure.
Record time Construction: BellPower was built in four months (from June to October).
The BellPower plant was built in only one phase.
- Reduction of 9.715 tons of CO2 emissions per year.
- A total of 12.950 MWh of electricity are generated per year.
- The construction of this kind of plant allowed for the generation of employment in the region.